Longgun Town Agrivoltaic Project with Supporting Energy Storage
25MW/50MWh
The project adopts a liquid-cooled energy storage system, con-sisting of TrinaStorage Elementa King Kong 1 battery cabinequipped with Trina Energy Storage self-developed 280Ahcells and TrinaTec integrated inverter-booster cabin.
The project was completed and put into grid-connected opera-tion and delivery within 90 days.
Highly efficient and energy-saving outdoor solar lights for municipal use
15MW/30MWh
The project is Trina Solar’s first integrated PV-energy storage demonstration power station.
It adopts 600W+ high-efficiency modules and Trina air-cooledenergy storage system.
Adopting the model of “New Energy + Mine Ecological Gover-nance”, it helps advance the ecological restoration of aban-doned land from historical legacy mines in Baiyin City.
15MW/30MWh
Feicheng Shiheng Town Agricultural-PV & Fishery-PV Complementary Project
28.832MW/53.664MWh
The project adopts Trina Solar’s integrated PV-energy storage solution.
An energy storage system with a capacity of26.832MW/53.664MWh is expanded approximately 800meters to the east of the booster station.
It adopts Trina self-developed and self-produced 280Ah lithiumiron phosphate batteries, matching Trina’s 1500V systemdesign solution.